20. September 2026

New bridge over the A70 near Hallstadt successfully moved into position

410 tonnes of steel structures, around 1,300 tonnes total weight and only about twelve hours of full closure: On the night of September 18–19, 2026, the new bridge at the Hallstadt interchange was successfully moved into its final position. Zeman & Co was responsible for shop planning, production and installation of the steel construction scope.

Entrance Gate
1,300 tonnes on 1,180 hp ©Zeman & Co

The approximately 50 m long and 15 m wide composite steel bridge was largely completed next to the motorway and then moved into its final position across the A70 during a night-time full closure.

At the time it was moved into position, cast asphalt, the guardrail and the noise barrier wall, among other elements, had already been installed. This high degree of completion meant that work directly above the motorway could be reduced to a minimum. The full closure of the A70 was therefore limited to around twelve hours.

Complex geometry and different structural systems

Zeman & Co took on shop planning, production and installation of the steel construction scope for the project. The installation scope also included planning the move-in operation.

The key technical challenges included the bridge’s complex geometry and asymmetric design. The main girders feature different structural systems: a truss structure is used on one side, and a box girder on the other.

The tight schedule also placed high demands on planning, production and installation. Especially when moving the nearly completed structure into position, every step had to be coordinated precisely.

Around 1,300 tonnes in motion

For the move-in, the overall structure weighing around 1,300 tonnes was moved using a modular heavy-load transport system. During the full closure, the bridge was transported across the motorway and positioned to the millimetre in its final location.

The new structure replaces the previous bridge at the Hallstadt interchange. Unlike the old design, the new bridge requires no supports in the area of the motorway lanes. A noise barrier wall is integrated on one side, while the opposite side remains open.

An in-depth look at the project and the move-in operation is provided by TV Oberfranken (TVO). Alexander Gebhart from IB Hofmann, project manager for construction supervision / construction monitoring, explains the key steps:

TVO: “1,300 tonnes on 1,180 hp: Spectacular bridge installation on the A70 near Hallstadt”

YouTube video blocked

By loading the video, you consent to embedded YouTube videos being loaded on this website. Data is transferred to Google/YouTube. Your consent is valid for 365 days and is stored in this browser. You can withdraw your consent at any time in the privacy policy.

BILD: Bridge construction almost overnight – 1,300-tonne bridge installed on A70

YouTube video blocked

By loading the video, you consent to embedded YouTube videos being loaded on this website. Data is transferred to Google/YouTube. Your consent is valid for 365 days and is stored in this browser. You can withdraw your consent at any time in the privacy policy.

Many thanks to our project team and all partners involved for the excellent and solution-oriented cooperation.

Client of Zeman & Co: Josef Rädlinger Ingenieurbau GmbH
Developer: Die Autobahn GmbH des Bundes, Northern Bavaria branch